I was working at a high-rise. 700+ units. 55% turnover that year. That’s about 385 turns.
Every one of them was a full CapEx turn. Paint, flooring, carpet and appliances, plus the typical maintenance turn to make sure everything worked.
Our vendors couldn’t keep up. Some days we had 5 or 6 paints or cleans. One week we had 25 turns.
It was a mess. It was a turn season I’ll never forget.
The board couldn’t keep up
We had a digital make-ready board. It wasn’t available on mobile.
So it was print out the sheet, go do the work, come back and update.
If a vendor missed an assignment or their day slipped, it was a manual click to change the date. That change cascaded, and it wasn’t very well put together.
We tried going back to the white board. With 10 to 15 turns a week, we could barely fit a month on there.
Spreadsheet, white board or a screen in the office, it fails the same way.
It isn’t connected. You can’t send it to a tech in the field. The white board doesn’t travel. And it carries information for weeks, until the turn plan is messy and unworkable.
The spreadsheet tells you the unit is late. It can’t tell you why.
It’s a project, not a list
It wasn’t just turning a lot of units. It was a massive project management task, with milestones and critical dates shifting almost daily. To be honest, it was nearly impossible to keep up with.
So we triaged. Leased vs. not leased. What can wait. Which move-in has padding, so that turn can drift and we can get the rented ones done.
A few still missed their dates. We transferred residents from the unit they rented to another ready one. Or we put them in hotels and paid for their movers to come back a day or two later.
We got through it with ingenuity and determination.
But nobody should have to.
Why turns actually run late
If it’s not volume or poor planning, it’s usually a surprise at the move-out inspection. Damage we didn’t know about and didn’t plan for. Pre-move-out inspections help, but they’re not always something we can do.
Your actual turn time is dictated by the condition of the unit after you get keys. Most fit the 5-day window. Sometimes it’s a mess and turns into a real project.
The clock starts at keys, not at the notice.
The other common cause is the vendor who over promises and under delivers. When the service contract was signed, someone forgot to ask one question:
“How many can you do per day?”
You find out when you assign 5 turns in a day and they can only do 3.
None of that shows up on the board.
Ready means ready
When the board is wrong, leasing ends up showing units that aren’t ready.
A ready unit they can show leases faster than a printed PDF floor plan.
Here’s how a unit gets signed off as ready. The tech says it’s done. The maintenance manager does a quality control inspection. Then somebody from the office does theirs.
Maintenance is looking for function, the big picture stuff. Walls painted. Cabinets straight. Appliances working. Air conditioning works. No big stains in the carpet.
The leasing team is looking for aesthetics and cleanliness. Piles of dust behind the doors. Specks of paint on the hinges. Blinds in the right position. Carpet looks good, floors are clean. What they’re asking is, can I sell this unit to a prospect?
Any deficiencies from both inspections get completed. When everybody’s in agreement that it’s done, then it goes on the market.
Vacancy loss is never recovered
At today’s national average rent, a vacant day costs about $60.
Say you have a 350-unit property with 40% turnover in a 12-month period. That’s 140 turns.
If even just 10% of those turns are 1 day late, that’s $840.
If 50% of them are 1 day late, that’s $4,200.
One study estimates most turns actually take 6 to 10 days, against a 5-day goal. On that same property, that would be 1 to 5 extra days on every turn, or $8,400 to $42,000 a year.
That’s before the hotel rooms, the movers, the transfers, and a new resident whose first day was a mess.
And the unleased units you let drift during triage? Those are vacant days too.
Vacancy loss is never recovered.
Once the day is gone, so is the rent.
Fix it in the slow season
Turn season is busy between May and the end of August.
September through April is when you fix it.
- Ask it. Talk with your existing vendors and find out how many they can do per day. Ask before you need it, not when you assign five.
- Back it up. More than one vendor for each task.
- Stage it. If there’s a CapEx project, find room for the appliances.
- Staff it honestly. With the current labor shortage for maintenance techs, you should always assume you’re down one tech when you’re doing long-term planning.
Looking back, the fix that year wasn’t more effort.
Someone should have paid more attention to how many turns were landing each day, recognized the volume was more than the site team and the vendors could handle, and shifted the turns to match what they could actually do.
When the count is more than your team can handle, it’s a conversation with the property manager on what reality is. Property managers typically want staggered leases too, so they don’t have to lease so many at once.
Nobody wants to lease 25 apartments in one week.
Evaluate the staff plan, vendor availability and lease staggering. Find that sweet spot of turns and leases that everyone can live with.
One thing to do this week
Pull next year’s lease expirations. Count the turns per week from May through August. Then put that number next to what your vendors can do per day, and what your site team can handle with the staffing plan you have. Assume you’re down one tech.
If it doesn’t fit, you can find out this week. Or you can find out in May.